Problems Faced At Site - Project Report - Multistoried Boys Hostel

posted in Project Reports | Email This Post Email This Post

Problems Faced At Site

There were numerous problems which were faced at site. Some of these were purely due to the human errors and poor workmanship but some were due to unseen factors.

  1. There was a problem in providing beams at one location as per the standard drawings so the drawings were changed by consulting the structural designers and architect
  2. There was problem pouring concrete in one beam due to small area available for pouring and compacting. The solution to this problem was that the size of steel was increased but the number of steel bars was decreased so as to provide the total area same.
  3. No window was there in staircases which lead to complete darkness, so it was decided to change the drawing by consulting the concerned authorities.
  4. The depth if beam above the door was 3’5” earlier but to keep the size of the door as per the standard it was changed to 3’.
  5. Frequent power cuts lead to increase in the cost of construction as generators were used to meet the power requirements
  6. Laying of foundations was postponed by 1 month due to the rainy season.
Related Posts :

There are currently 2 responses to “Problems Faced At Site - Project Report - Multistoried Boys Hostel”

Why not let us know what you think by adding your own comment! Your opinion is as valid as anyone elses, so come on... let us know what you think.

  1. 1 On April 23rd, 2008, muthu said:

    thank u very much u should have to post more thing s like this it will much usefull for beginner like me

  2. 2 On August 5th, 2008, manimaran said:

    hi,
    im maran,i ve finished in civil engineering then im doing M.E(construction engg mgt).
    i ve seen ur six month training project report very nice and very good.i ve studied ur reports,
    i ve learned about lot of thing and technical point…….
    thank you …

Leave a Reply