INITIAL AND FINAL SETTING TIME
We need to calculate the initial and final setting time as per IS: 4031 (Part 5) – 1988. To do so we need Vicat apparatus conforming to IS: 5513 – 1976, Balance, whose permissible variation at a load of 1000g should be +1.0g, Gauging trowel conforming to IS: 10086 – 1982.

Procedure to determine initial and final setting time of cement
i) Prepare a cement paste by gauging the cement with 0.85 times the water required to give a paste of standard consistency.

ii) Start a stop-watch, the moment water is added to the cement.

iii) Fill the Vicat mould completely with the cement paste gauged as above, the mould resting on a non-porous plate and smooth off the surface of the paste making it level with the top of the mould. The cement block thus prepared in the mould is the test block.

Advertisements

A) INITIAL SETTING TIME
Place the test block under the rod bearing the needle. Lower the needle gently in order to make contact with the surface of the cement paste and release quickly, allowing it to penetrate the test block. Repeat the procedure till the needle fails to pierce the test block to a point 5.0 ± 0.5mm measured from the bottom of the mould.The time period elapsing between the time, water is added to the cement and the time, the needle fails to pierce the test block by 5.0 ± 0.5mm measured from the bottom of the mould, is the initial setting time.

Advertisements

B) FINAL SETTING TIME
Replace the above needle by the one with an annular attachment. The cement should be considered as finally set when, upon applying the needle gently to the surface of the test block, the needle makes an impression therein, while the attachment fails to do so. The period elapsing between the time, water is added to the cement and the time, the needle makes an impression on the surface of the test block, while the attachment fails to do so, is the final setting time.

Share this post

Kanwarjot Singh

Kanwarjot Singh is the founder of Civil Engineering Portal, a leading civil engineering website which has been awarded as the best online publication by CIDC. He did his BE civil from Thapar University, Patiala and has been working on this website with his team of Civil Engineers.

If you have a query, you can ask a question here.

101 comments on "Test To Check Initial And Final Setting Time Of Cement"

varun bhardwaj says:

I self varun bhardwaj fron mmmec gorakhpur. I WANT TO CHECK CIEMENT BY TESTING BECAUSE THIS IS MY PROJECT IN CIEMENT

naresh kumar says:

initial time is 30 minutes and final setting time is 600 minutes….

Aarushi says:

answer me following,,,
1) Importance of the test. with reference to chemical composition of cement and its hydrolysis properties?
2) normal results expected?
3)use of retarders?
4) use of additives to change setting time and its importance?
5) results of deviation of actual results from expected results?

Ezra says:

At what time does initial or final setting time start and end?and how do you give the results to students?

Suraj Ram says:

The initial setting time of ppc is 30 minutes and final setting time is 10 hours

E.Prasad says:

why need of this test

Nitin jain says:

my project on the high volume fly ash mortar so we need to check cement. we are using ppc cement but the intial and final setting time of ppc cement different from opc cement.could it possible.

Adil says:

I am also planning to do a project on high volume flash .pls help me

Akhtar pathan says:

Yes it is 100% possible because only difference in ppc and opc is initial and final setting times
Opc take a little time for setting and ppc take a long time for setting.

Mustaq says:

Well i need help for structural analysis??

Md.Nuruzzaman says:

Sir,I am engineer.But i want to know difference between “port land cement and ordinary port land cement”also which are better cement for High rise building?

ANSHU BHARDWAJ says:

Sir, i m doing job in SGS INDIA PVT. LTD. as an inspection engineering. So i want to know that hw can i check the cement concrete ratio on site. Pls tell me the process of checking c/c ratio.

asela wimu says:

what is the errors these practicals

md nadeem says:

Initial setting time is about 30 minutes
Final setting time is about 10-12 hours…………

mohd masood raza says:

what is insulating material

lokeswara rao says:

Sir i am an filed engineer I am inspected a cement brick factory there use opc 53 grad cement but the problem is after 3 days of curing the brick edges should breaks after 7 days curing the brick is good.why setting of brick is slow.

ahmed says:

Do the initial setting time & final setting time differ in cements i.e. in OPC, PPC, SRC etc.

Thamindu says:

yeah it differs

Mohideen says:

Sir what is the initial setting time of concrete using retarder
Example am using Ordinary Portland Cement with retarder conplast RP264

WAQAR AHMAD says:

not less than 45 minutes

Khandapu Rambabu says:

Intial setting time shall not be less than 30minutes.and final setting timing shall not be greater than 600minutes for OPC.For special type of cement it will vary

sumit chauhan says:

why we take water 85% of con for setting time of cement standard consistency.
as we have caculated the water 32% in standard consistancy test

adel siroosi says:

is there any difference when we test as bellow:
– at first time when cement produced we test the initial setting time which it was 100 minutes
– after 3 months we checked same sample and get this result: initial setting time was 150 minutes
so is this result correct? if yes, what is the reason?

Badal Kumar Majhi says:

what is the soundness test of cement.

Leave a Reply

Your email address will not be published. Required fields are marked *

Ask a question