What is the function of introducing cement plug before pouring concrete in bored piles?

It is a common practice in the construction of bored piles by adding a cement plug before concreting of bored piles takes place. One of the possible explanations is that the cement grout serves as a barrier and protects fresh concrete from being washed away by water inside pile bore.

The cement grout helps to set aside water when the first batch of concrete is poured down from the tremie pipe. As such, the quality of fresh concrete is anticipated not to be seriously affected by water and this helps to improve toe imperfection problem.

Advertisements

This question is taken from book named – A Closer Look at Prevailing Civil Engineering Practice – What, Why and How by Vincent T. H. CHU.

Share this post

Kanwarjot Singh

Kanwarjot Singh is the founder of Civil Engineering Portal, a leading civil engineering website which has been awarded as the best online publication by CIDC. He did his BE civil from Thapar University, Patiala and has been working on this website with his team of Civil Engineers.

If you have a query, you can ask a question here.

Leave a Reply

Your email address will not be published. Required fields are marked *

Ask a question