It is a common practice in the construction of bored piles by adding a cement plug before concreting of bored piles takes place. One of the possible explanations is that the cement grout serves as a barrier and protects fresh concrete from being washed away by water inside pile bore.
The cement grout helps to set aside water when the first batch of concrete is poured down from the tremie pipe. As such, the quality of fresh concrete is anticipated not to be seriously affected by water and this helps to improve toe imperfection problem.