Awarded as the best online publication by CIDC
It appears to be a common construction practice that bored piles are normally cast up to a piling platform much higher than the formation level of pile caps. Then, the excessive pile length has to be cropped and removed to the correct level for the subsequent construction of pile cap. The reasons of such practice are as follows:
(i) It is technically sound to employ such practice because laitance, impurities and poorly-compacted concrete should have migrated to the top of the piles. Therefore, additional length at the top of piles is constructed to accommodate these sub-standard concrete, which are subsequently removed and cropped to leave high quality concrete over the entire length of piles.
This question is taken from book named – A Closer Look at Prevailing Civil Engineering Practice – What, Why and How by Vincent T. H. CHU.
If you have a query, you can ask a question here.
how much length of latience concrete pile head is to be removed for bored pile cast in situ of 1200mm dia to 1500mm dia.