What is the purpose of maintaining excess water head during excavation for bored piles?

Posted in Piles Engineering | Email This Post Email This Post |
Print Friendly, PDF & Email

Excavation of bored piles is usually implemented by a hammer grab. The steel casing will be extended by welding or bolting on additional casing and is installed by hydraulic oscillator.

Water is pumped into the casing during excavation and excess water head is required to be maintained to prevent any ingress of material at the bottom of casing. Moreover, for excavation below pile casing, the provision of excess water head is essential to maintain bore stability.