Awarded as the best online publication by CIDC

Comparing the rate of “Formwork exceeding 300mm wide, horizontal or at any inclination up to and including 5o to the horizontal” with the rate of “Formwork exceeding 300mm wide, at any inclination more than 85o up to and including 90o to the horizontal”, which one is higher?

tem “Formwork exceeding 300mm wide, at any inclination more than 85o up to and including 90o to the horizontal” refers to formwork formed vertically and when compared with formwork erected in horizontal plane, the amount of falsework required is smaller.

The item “Formwork exceeding 300mm wide, horizontal or at any
inclination up to and including 5o to the horizontal” refers to formwork to be erected in horizontal position and in general it requires much falsework to support this type of formwork. Therefore, the rate for this item is higher than the one mentioned in the above paragraph.

Advertisements

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Share this post

Kanwarjot Singh

Kanwarjot Singh is the founder of Civil Engineering Portal, a leading civil engineering website which has been awarded as the best online publication by CIDC. He did his BE civil from Thapar University, Patiala and has been working on this website with his team of Civil Engineers.

If you have a query, you can ask a question here.

One comment on "Comparing the rate of “Formwork exceeding 300mm wide, horizontal or at any inclination up to and including 5o to the horizontal” with the rate of “Formwork exceeding 300mm wide, at any inclination more than 85o up to and including 90o to the horizontal”, which one is higher?"

shrikant says:

I need rate analysis of Formwork for Different works like Footings, Columns, Beams etc. etc.
Also what is composite rate analysis of RCC. Can any body Explain me @ it?

Leave a Reply