In deep excavation, adjacent ground water table is drawn down which may affect the settlement of nearby buildings. What is the remedial proposal to rectify the situation?

Posted in Piles Engineering | Email This Post Email This Post |
Print Friendly, PDF & Email

One of the methods to control settlement of nearby buildings due to excavation work is by recharging. Water collected in wells in deep excavation is put back to the top of excavation in order to raise the drawn-down water table.

The location of recharge should be properly selected to ensure the soil is sufficiently permeable to transfer the pumped water back near the affected buildings.

Advertisements

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

More Entries :
Comments
  • Adil Aziz April 29, 2013 at 3:29 am

    Then what about PVD. Is PVD also affecting the near by structures…

  • lawrence loke May 6, 2016 at 2:14 am

    How to determine the suitable spacing for recharge wells?