Why are intermediate jacks designed in some pipe jacking projects?

Posted in Tunneling | Email This Post Email This Post

When the process of pipe jacking stops, building up of resistance is very fast in some soil. For instance, increase in jacking force of 20%-40% is required for a stoppage of pipe jacking for just several hours. Hence, it is recommended that pipe jacking should be carried out in a continuous operation.

For a long pipeline, the frictional forces established between the jacking pipes and soil is high. Sometimes, such resisting forces may be so high that they can hardly be overcome by the jacks in jacking pits. Moreover, even if the jacks can overcome the high frictional forces induced during jacking, high loads are experienced in jacking pipes during driving. Jacking pipe’s material e.g. concrete may not have sufficient strength to resist these stresses and hence pipe strength is another factor that governs the need for consideration of using intermediate jacks.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

More Entries :

Share Information

What is Civil Engineering

Journals Books And Softwares

Branches Of Civil Engineering

Civil Engineering Jobs

Knowledge Center

Civil Engineering Universities/Events

Gallery - Civil Engineering Pictures

Search


Author

Top Contributors

Yahoo Group - Civil Engineering Portal

Subscribe to EngineeringCivil.com


Powered by groups.yahoo.com

Recently Added

Civil Engineering Links

Spread the Word