What is the purpose of maintaining excess water head during excavation for bored piles?

Posted in Piles Engineering | Email This Post Email This Post

Excavation of bored piles is usually implemented by a hammer grab. The steel casing will be extended by welding or bolting on additional casing and is installed by hydraulic oscillator. Water is pumped into the casing during excavation and excess water head is required to be maintained to prevent any ingress of material at the bottom of casing. Moreover, for excavation below pile casing, the provision of excess water head is essential to maintain bore stability.

This question is taken from book named – A Closer Look at Prevailing Civil Engineering Practice – What, Why and How by Vincent T. H. CHU.

More Entries :

Comments

Share Information

What is Civil Engineering

Journals Books And Softwares

Branches Of Civil Engineering

Civil Engineering Jobs

Knowledge Center

Civil Engineering Universities/Events

Gallery - Civil Engineering Pictures

Search


Author

Top Contributors

Yahoo Group - Civil Engineering Portal

Subscribe to EngineeringCivil.com


Powered by groups.yahoo.com

Recently Added

Civil Engineering Links

Spread the Word