Is the quality of concrete impaired by free-falling concrete placement method in bored piles?

Based on the research by STS Consultants Ltd., it was found that concrete placed by free falling below 120 feet would not suffer from the problem of segregation and the strength of concrete would not be detrimentally impaired provided that the piles’ bore and base are dry and free of debris. Moreover, it is presumed in the past that during free falling of fresh concrete into the pile bores the hitting of falling concrete in the reinforcement cage causes segregation. However, in accordance with the experimental results of STS Consultants Ltd., the striking of reinforcement cage by fresh concrete does not have significant effect on the strength of concrete

In addition, for long bored piles, it is impractical to conduct vibration to concrete. For concrete placed by free falling method, the impact action arising from free falling is assumed to induce adequate vibration. On the other hand, concrete placed by tremie method appears to be lack of vibration and this may affect the strength and integrity of concrete. The research results showed that the strength of vibrated concrete was slightly higher than unvibrated concrete. Vibration proved to have added advantage to concrete strength but not essential to achieve the design pile strength.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Is pile tip cover necessary for rock-socketed H-piles?

In current practice concrete cover is usually provided at the pile tips of pre-bored H-piles socketed in rock. The purpose of such arrangement is to avoid the potential occurrence of corrosion to H-piles in case concrete cover is not designed at pile tips. However, recent field and laboratory observations had reservation of this viewpoint. In case H-piles are designed to be placed directly on top of rock surface, it provides the tip
resistance to limit the pile movement in the event of bond rupture between grout and H-piles. As such, some contractors may choose to tamp the H-piles by using drop hammers to ensure the H-piles are founded directly on top of rock surface. Practically speaking, it poses difficulties during the process of tamping because there is a chance of possible buckling of long H-piles when too much energy is provided to the piles.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Why is sleeving applied in piles constructed on slopes?

For high-rise buildings constructed on steep cut slopes, these buildings are usually supported by large diameter piles. Though the piles are founded at some depth below the slopes, lateral load arising from wind on buildings may induce loads on the slop and causes slope failures. For shallow depths of slope which is marginally stable, it is more vulnerable to slope failure.

Hence, an annulus of compressible material called sleeving is introduced in piles so as to reduce the transfer of lateral loads from buildings to slopes.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

What is the purpose of shaft grouting of deep foundations?

In shaft grouting operation, tube-a-manchette pipes are fixed at regular spacing to the reinforcement cage. After concreting barrettes/bored piles, a small volume of water is injected under high pressure into these pipes to crack the concrete. The cracking process should be carried out within 24 hours after concreting. The purpose of cracking is to create a path for grout to go through. About a week after concreting of barrette, grouting is then carried out in these pipes to improve the friction between the foundation and the surrounding soils.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Can down the hole hammer function below water table?

Down the hole hammer has been used extensively to form pre-bored holes as rock sockets for mini piles and pre-bored H piles. The hammer functions by driving repeatedly a drill bit using compressed air on the rock. However, the use of down the hole hammer is normally limited to hole diameter of 600mm.

In using down the hole hammer, compressed air serves to drive the drill bit and to expel the cuttings which are blown out to the air at ground level. However, for driving the hammer about 30m below ground water level, the air pressure has difficulty in coping with great water pressure. Moreover, blowing of cuttings by compressed air also dewaters the nearby soils. As a result, settlement of nearby ground may occur which is undesirable.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Page 2 of 2212345...1020...Last »

Share Information

What is Civil Engineering

Journals Books And Softwares

Branches Of Civil Engineering

Civil Engineering Jobs

Knowledge Center

Civil Engineering Universities/Events

Gallery - Civil Engineering Pictures

Search


Author

engineeringcivil.com awarded best online publication by CIDC 2013

Top Contributors

Yahoo Group - Civil Engineering Portal

Subscribe to EngineeringCivil.com


Powered by groups.yahoo.com

Recently Added

Civil Engineering Links