INITIAL AND FINAL SETTING TIME
We need to calculate the initial and final setting time as per IS: 4031 (Part 5) – 1988. To do so we need Vicat apparatus conforming to IS: 5513 – 1976, Balance, whose permissible variation at a load of 1000g should be +1.0g, Gauging trowel conforming to IS: 10086 – 1982.

Procedure to determine initial and final setting time of cement
i) Prepare a cement paste by gauging the cement with 0.85 times the water required to give a paste of standard consistency.
ii) Start a stop-watch, the moment water is added to the cement.
iii) Fill the Vicat mould completely with the cement paste gauged as above, the mould resting on a non-porous plate and smooth off the surface of the paste making it level with the top of the mould. The cement block thus prepared in the mould is the test block.

A) INITIAL SETTING TIME
Place the test block under the rod bearing the needle. Lower the needle gently in order to make contact with the surface of the cement paste and release quickly, allowing it to penetrate the test block. Repeat the procedure till the needle fails to pierce the test block to a point 5.0 ± 0.5mm measured from the bottom of the mould.The time period elapsing between the time, water is added to the cement and the time, the needle fails to pierce the test block by 5.0 ± 0.5mm measured from the bottom of the mould, is the initial setting time.

B) FINAL SETTING TIME
Replace the above needle by the one with an annular attachment. The cement should be considered as finally set when, upon applying the needle gently to the surface of the test block, the needle makes an impression therein, while the attachment fails to do so. The period elapsing between the time, water is added to the cement and the time, the needle makes an impression on the surface of the test block, while the attachment fails to do so, is the final setting time.

More Entries :

Comments
  • praveen kumar April 9, 2009 at 12:04 pm

    respected sir/madam

    can you send me, what are the test conducted for concrete? please

  • gz June 14, 2009 at 7:41 pm

    slump test
    compressive strength / density
    workability

  • mark fuster July 21, 2009 at 5:44 am

    i wan to know the various testes of cement

  • Salisu Abba August 7, 2009 at 5:47 pm

    Sir/Madam,
    Tanx alot for helping me with information partaining my discipline.

  • LSD October 6, 2009 at 3:03 am

    I need to know importance of setting time.

  • madhukar November 3, 2009 at 8:35 am

    can u send me the different test conducted on cements and their permissible limits of the tests conducted

  • Olonade November 12, 2009 at 5:36 pm

    I really found your site educating. pls, kindly send to me the comparsion between the test procedures on cement, fresh mortar and concrete based on IS, BS and ASTM standards.

  • knl December 28, 2009 at 8:40 am

    thanx….

  • M Usman Aziz January 10, 2010 at 9:14 am

    hello…… know i think the details on this site about initial and final setting time of cement practical is not satisfactory……………… please send me the details of this practical i want to make my assignment on this topic……

  • dipendra khetan January 23, 2010 at 3:21 am

    dear sir i wanted to know the lab test report of varoius cement pls help me out

  • Oyediran hafiz February 5, 2010 at 5:31 pm

    Goodday sir/ma
    i need the time range for the intial and final setting time so i can use it as a bench mark for my results.

  • what is the final settig time of cement or concrete March 25, 2010 at 1:16 pm

    plz sir i want to know what is final setting time of portland cement

  • YARED March 29, 2010 at 12:23 pm

    WHY,IT WAS VERY CRUCIAL TO KNOW THE INITIAL AND FINAL SETTING TIME FOR CONCRETE MIX DESIGN.

  • farid March 30, 2010 at 4:46 am

    what is the ideal time difference between initial and final setting

  • asb April 24, 2010 at 5:09 am

    thx for the work provided

  • isaac April 24, 2010 at 8:05 am

    so educative. can u post the importance of initial and final setting time for cement

  • IBRAHIM May 3, 2010 at 6:44 am

    Is ther a term in the Cement Testing Process called “Initial False Setting Time”? If so, please explain to me. So many thanks in advance.

  • Ashok nce(nalanda) May 17, 2010 at 8:11 am

    This site very much help me for the preparation of university exam.

  • mangesh May 25, 2010 at 4:15 am

    What i sthe correct time to start to chechk for initial setting and then for final setting of cement.

  • Billy Yang May 28, 2010 at 8:21 am

    I would like to know why must you find the initial and setting time of cement?

1 2 3 4

Share Information

What is Civil Engineering

Journals Books And Softwares

Branches Of Civil Engineering

Civil Engineering Jobs

Knowledge Center

Civil Engineering Universities/Events

Gallery - Civil Engineering Pictures

Search


Author

Top Contributors

Yahoo Group - Civil Engineering Portal

Subscribe to EngineeringCivil.com


Powered by groups.yahoo.com

Recently Added

Civil Engineering Links

Spread the Word