Should on-site addition of water to fresh concrete be allowed?

Posted in Concrete Engineering | Email This Post Email This Post

The addition of water to fresh concrete in truck mixer upon arrival at the location of concrete is allowed only if some design mixing water is held back during initial mixing stage. Addition of water in excess of design mixing water would definitely cause an increase of water cement ratio leading to a reduction of concrete strength.

The purpose of adding water to fresh concrete is to increase the workability to facilitate placement of concrete. The use of water-reducing agent or superplasticizer could help resolve the problem but extra attention has to be paid on the segregation issue. In case there is some buffer in the amount of water in fresh concrete so that addition of water would not result in exceeding the designed water cement ratio, water could be added based on the following rule of thumb: 5 liters of water per m3 of concrete gives about 25 mm increase in slump.

This question is taken from book named – A Closer Look at Prevailing Civil Engineering Practice – What, Why and How by Vincent T. H. CHU.

More Entries :

Comments
  • Murtiza July 27, 2011 at 6:45 am

    This site is very useful for every eng. Students,especialy for those stds who can’t aford 2 buy costly books.most apreciable thing is that it gives priceless information within seconds.thanku very very much….

Share Information

What is Civil Engineering

Journals Books And Softwares

Branches Of Civil Engineering

Civil Engineering Jobs

Knowledge Center

Civil Engineering Universities/Events

Gallery - Civil Engineering Pictures

Search


Author

Top Contributors

Yahoo Group - Civil Engineering Portal

Subscribe to EngineeringCivil.com


Powered by groups.yahoo.com

Recently Added

Civil Engineering Links

Spread the Word