In incremental launching method of bridge construction, what are the measures adopted to enhance sufficient resistance of the superstructure during the launching process?

Posted in Bridge Engineering | Email This Post Email This Post

(i) During the launching process the leading edge of the superstructure is subject to a large hogging moment. In this connection, steel launching nose typically about 0.6-0.65 times span length is provided at the leading edge to reduce the cantilever moment. Sometimes, instead of using launching nose a tower and stay system are designed which serves the same purpose.

(ii) The superstructure continually experiences alternative sagging and hogging moments during incremental launching. Normally, a central prestress is provided in which the compressive stress at all points of bridge cross section is equal. In this way, it caters for the possible occurrence of tensile stresses in upper and lower part of the cross section when subject to hogging and sagging moment respectively. Later when the whole superstructure is completely launched, continuity prestressing is performed in which the location and design of continuity tendons are based on the bending moments in final completed bridge condition and its provision is supplementary to the central prestress.

(iii) For very long span bridge, temporary piers are provided to limit the
cantilever moment.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

More Entries :

Comments

Share Information

What is Civil Engineering

Journals Books And Softwares

Branches Of Civil Engineering

Civil Engineering Jobs

Knowledge Center

Civil Engineering Universities/Events

Gallery - Civil Engineering Pictures

Search


Author

Top Contributors

Yahoo Group - Civil Engineering Portal

Subscribe to EngineeringCivil.com


Powered by groups.yahoo.com

Recently Added

Civil Engineering Links

Spread the Word