If on-site slump test fails, should engineers allow the contractor to continue the concreting works?

Posted in Concrete Engineering | Email This Post Email This Post

This is a very classical question raised by many graduate engineers. In fact, there are two schools of thought regarding this issue.

The first school of thought is rather straightforward: the contractor fails to comply with contractual requirements and therefore as per G. C. C. Clause 54 (2)(c) the engineer could order suspension of the Works. Under the conditions of G. C. C. Clause 54(2)(a) – (d), the contractor is not entitled to any claims of cost which is the main concern for most engineers. This is the contractual power given to the Engineer in case of any failure in tests required by the contract, even though some engineers argue that slump tests are not as important as other tests like compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other contractual requirements e.g. compression test. This is based upon the belief that workability is mainly required to achieve design concrete compression strength. In case the compression test also fails, the contractor should demolish and reconstruct the works accordingly. In fact, this is a rather passive way of treating construction works and is not recommended because of the following reasons:

(i) Workability of freshly placed concrete is related not only to strength but also to durability of concrete. Even if the future compression test passes, failing in slump test indicates that it may have adverse impact to durability of completed concrete structures.

(ii) In case the compression test fails, the contractor has to deploy extra time and resources to remove the work and reconstruct them once again and this slows down the progress of works significantly. Hence, in view of such likely probability of occurrence, why shouldn’t the Engineer exercise his power to stop the contractor and save these extra time and cost?

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

More Entries :

Comments
  • mahmoud refaat March 11, 2011 at 8:16 pm

    In concrete compression test, normally 150mmx150mmx150mm concrete cube samples is used for testing. Why isn’t 100mmx100mmx100mm concrete cube samples used in the test instead of 150mmx150mmx150mm concrete cube samples?

  • BRIGHT ADOMAKO APPIAH March 27, 2011 at 5:10 pm

    I am so grateful and appreciative of perfect exiguous informative materials that is often on the net studies. thanks

  • Quality Controler January 4, 2012 at 12:41 pm

    It is allowed to add chemical to concrete upon pouring as the contractors blaming that they can not pour the concrete inside columns even it has passed the slump test please if yes which kind of chemical ?

Share Information

What is Civil Engineering

Journals Books And Softwares

Branches Of Civil Engineering

Civil Engineering Jobs

Knowledge Center

Civil Engineering Universities/Events

Gallery - Civil Engineering Pictures

Search


Author

Top Contributors

Yahoo Group - Civil Engineering Portal

Subscribe to EngineeringCivil.com


Powered by groups.yahoo.com

Recently Added

Civil Engineering Links

Spread the Word